Monday, 15 February 2016

Catching up with winter projects

The high rainfall over the winter period has delayed winter project works at the golf club, especially work involving earth moving.
The green-staff have been busy over the last couple of weeks now that the soil profile has dried out a little. A 3.5 tonne excavator has been hired in and put to work on the following projects.



The pond in front of the 9th Tee has been re-profiled to allow easier access and maintenance of the surrounding grass land. 
The old 9th winter Tee which was sited at the side of the pond has been removed with the surrounding area re-contoured, again, to allow easier access with mowers. 
Some of the spoil from the Tee area was used to build a base for the last practice Green being constructed on the bottom practice ground.




Re-shaping the ground around the pond


Construction of a 200 sq m base for the last pitching Green


The three fairway bunkers situated on the 1st hole have now been removed and the landing area re-contoured to encourage golfers to target the 1st fairway instead of bailing out onto the 18th hole.


The three bunkers before removal, bland round holes in the ground which did not replicate the original course architects ethos and discouraged golfers from playing down there own fairway. 


Ongoing work


The first area ready for turfing


The hired in excavator was also put to work clearing and tidying our main material dumping ground to the left of the 2nd Green/hole.





Wednesday, 13 January 2016

development of three practice pitching Greens

The main project on the golf course this winter has been the development of three practice pitching Greens on the short practice ground. The project was originally planned to be completed by Christmas but the heavy rainfall this winter has delayed work. At this present time two of the Greens have been completed with the third commencing asap. We have been fortunate that the practice ground is one of the freer draining areas of the course and is situated near to the hard standing of the maintenance building allowing easy access.
All three Greens are designed with different shapes and contours allowing a wide range of practice pitch and chip shots.
Green 1 is relatively long and flat with a few undulations running through it. This will allow long running shots.
Green two is built into a ridge with two bunkers surrounding the Green. The bunkers have been surrounded with polypropylene grass carpet. This will aid easy maintenance and retain original levels following sand splash.
Green three is a target Green for longer pitching up to one hundred yards in length.
Four 4m x 2m high standard polypropylene mats are to be installed allowing various shot lengths to the three Greens. Shorter chip shots will be played from mown out fairway sections immediately surrounding each Green.



Above photo  of Green 1 during construction shows the shaped and consolidated base with the first rootzone layer being added.




One of the bunkers on Green 2, fitted with bunker mat liner and polypropylene grass to collect sand splash and retain levels.

Wednesday, 18 November 2015

Cut and collection of rough land areas



The photograph above shows the rough land area around the pond situated in front of the 9th Tee. The grass land has been mown and the arisings collected up. As part of the winter work other rough land areas around the golf course will have the same treatment. The larger accessible areas are mown with the tractor mounted "Amazone" which cuts and collects the grass.





Wednesday, 4 November 2015

Development of new short game practice area

Work has now commenced on the development of a three Green short game practice area on the bottom practice ground.
The main goal is to build three Greens, one at 200 sq m and two at 150 sq m in size. The contouring of the Greens will create a wide range of shots with the middle Green 2 having two bunkers built into the Green surround.



Early stages,turf clearing and levelling the old bunker on the 200 sq m Green 1


Green 1 will be set up for longer chip and run shots. The photo above shows the base of the Green built. There are some undulations in the base that do not show up in the photograph.


Thursday, 8 October 2015

Maintenance work to Greens 3, 4 and 6

In an attempt to improve the drainage rates on Greens 3, 4 and 6 extra aeration and sand dressing has been carried out.
The profile of these Greens is made up of a finer soil texture than others on the course and do not naturally drain as fast. For example the 7th, 9th and 18th Greens are constructed from a sandier material and with the help of their elevation naturally drain well.
Following discussions with the STRI it was decided to try and create vertical drainage channels which will help surface water percolate through the profile quicker. In achieving this the growing environment will improve and surface water following heavy rainfall will not sit on the Green surface for as long.
The work carried out involved verti-draining using 19mm diameter solid tines to a depth of 250mm. Dressing sand was then applied to the Green which was then brushed into the holes using a mechanical contra-rotating brush.
The Green was then hollow cored using 12mm diameter hollow tines to a depth of 63mm. Further dressing sand was  applied following overseeding with Brown top bent seed. The brush was again used to fill the holes full of sand. Altogether approximately 13 tonnes of sand was applied to the three Greens.


Verti-draining on a sanded Green



Hollow coring following verti-draining and sanding


The contra-rotating brush used to move the sand down the aeration holes

Thursday, 24 September 2015

Autumn maintenance work to Tees

Following on from last weeks Greens maintenance the main Teeing grounds have had some maintenance carried out to them.
All Tees have been double verti-cut followed by a single mow at 8mm height of cut. The new root zone constructed Tees were then verti-drained using 13mm diameter solid tines to a depth of 200mm. The older Tees have been hollow cored using 13mm diameter hollow tines to a depth of 63mm. All Tees will now be sand dressed applying approximately 20 tonnes of dressing sand.




Hollow coring the 17th Tee bed

Friday, 18 September 2015

Greens maintenance week 14th to 18th Sept

The maintenance work on the Greens  has gone to plan this year with the help of favourable weather. All Greens have been treated with the following:

Verti-cut (two passes)
Single mow at 3.5mm height of cut.
Sand dressing involving three dressings over the week applying approximately 50 tonnes of dressing sand.
Verti-drained using 13mm solid tines to a depth of 200mm.
Solid tine using 9mm diameter solid tines to a depth of 75mm.
Overseeding using 50Kg of browntop bent seed. (AberMajesty browntop bent blend)
Overseeding of the large putting Green with varieties of Fescue seed.



Sand dressing


Drag matting the sand into the Green surface